A Gantt chart is a project timetable drawn as bars. Tasks run down the left, time runs across the top, and the length of each bar shows how long that task takes. One glance tells you what is running, what is late and what could be done at the same time.

📘 What you need to know

Reading a Gantt chart

Opening a new bakery unit in nine weeks Each square is one week. Overlapping bars run together. TASK 1 2 3 4 5 6 7 8 9 A Design B Order kit C Fit out D Recruit E Train F Open Bars show when a task starts, how long it lasts and when it ends. Tasks A and B overlap, so they can run at the same time.
Task C cannot start until A finishes, so its bar begins in week 4. That gap is a dependency, and it is what fixes the finish date.

What the chart is telling you

TaskStartsLastsDepends on
A Design the unitWeek 13 weeksNothing
B Order equipmentWeek 14 weeksNothing
C Fit out the kitchenWeek 43 weeksA
D Recruit staffWeek 52 weeksB
E Train staffWeek 72 weeksC and D
F Opening weekWeek 91 weekE
Read the chart backwards to find what really controls the finish date. F waits for E, E waits for C, C waits for A. Those four are the chain that decides everything. B and D have slack, so a delay there costs nothing.

Worked examples

WORKED EXAMPLE

Using the chart above, state the total time the project is expected to take, and identify two tasks that can run at the same time. [3 marks]

Step 1: find where the last bar ends Task F ends at the close of week 9. Total project time = 9 weeks [1] Step 2: look for bars sitting side by side in the same weeks A and B both run in weeks 1 to 3 [1]. C and D both run in weeks 5 and 6 [1]. 9 weeks; A with B, and C with D “same time” always means the bars overlap horizontally
WORKED EXAMPLE

Task C overruns by two weeks. Explain the effect on the opening date. [3 marks]

Step 1: who is waiting on C? E cannot start until C is finished [1]. Step 2: follow the chain E is pushed from week 7 to week 9, and F is pushed from week 9 to week 11 [1]. Step 3: state the effect The opening is delayed by the full two weeks, because C has no spare time built into the schedule [1]. Opening slips from week 9 to week 11 a delay only matters if something is waiting on it
Not every delay costs you. If task D slipped by one week it would still finish before E needed it, so the opening date would not move at all. That spare time is called float, and it is the idea critical path analysis measures properly.

How useful are Gantt charts?

StrengthWeakness
Anyone can read it at a glance, including non-managersBig projects with dozens of tasks become unreadable
Shows planned progress against actual progressRedrawing it every time something moves eats management time
Makes it obvious which tasks can run togetherDoes not show how much labour or money each task needs
Helps schedule staff and deliveries for the right weekRigid: one change can force the whole chart to be rebuilt
Good for projects with clear, known stepsWeak for projects that keep changing shape as they go

💡 Exam tips

⚠ Common mix-ups

Up next: Comparing Cultures With Hofstede — projects and plans work differently in different countries. Hofstede gives you a structured way to compare them.

Want this explained one-to-one?

Book a free session with an experienced IB Business Management tutor and get your trickiest topics made simple.

Book a Free Session →